PHX North Runway 8-26 Improvements

CSW worked on this 1.7 million JOC project with a 21 day runway closure.  CSW worked around the clock to complete this work with 6 days to spare for final clean up and FOD completion.  This project involved heavy coordination and planning between PSHIA and CSW.  
  • 3,244 SY 22" runway panels removal and replacement
  • 1,200 FT electrical trenching
  • 32 lead in light cans added by trenching retro-fit conduit
Go to Aviation
 
Go to Services

 

 
This Project Required the Following Primary Services:


Concrete Construction 
CSW provides a wide variety of concrete construction work including curb and gutters, sidewalks, ramps and loading docks, underground concrete structures, box culverts, catch basins and junction structures, Portland Cement Concrete Paving (PCCP), headwalls, outfalls, and many other custom engineered structures.


Asphalt Paving 
CSW offers traditional cement-based asphalt paving and rubberized asphalt paving. Our in-house paver and traffic control team has been utilized on many projects of varying scope and complexity crossing several markets.

Pre-Construction - Grading/Earth Work - Utility Infrastructure - Concrete Construction - Asphalt Paving - Crushing/Pulverizing

Aviation - Industrial - Landfills - Mine Support - Site Work - Street Improvements

Sitemap

ROC Lic# 270136A